水土保持监理工作的程序与主要内容
作者:尼亚山木·塔西
来源:《中国建筑科学》2015年第01期
摘 要:水土保持监理工作总目标是根据国家—准得水土保持设计方案,按照国家有关的水土保持法规和工程水土保护规定,对工程承包商水土保持合同条款的执行情况进行监督和管理,促进水土保持项目按合同目标进行实施,防治施工活动造成的水土流失。 关键词:水土保持;监理工作;主要内容。
Supervision of soil and water conservation program and the main content Ni ya shan mu·ta xi
(xinjiang kuqa water bureau, xinjiang , kuqa 842000)
Abstract:soil and water conservation supervision work according to the national - must have to soil and water conservation is the total target design, in accordance with the relevant state laws and regulations of soil and water conservation and engineering of soil and water conservation, soil and water conservation to engineering contractors the terms of the contract implementation supervision and management, promote the implementation of water and soil conservation project according to the contract target, prevention and control of soil erosion caused by construction activities. Keywords:soil and water conservation; Supervision work; The main content. 1.水土保持监理工作程序
水土保持监理的工作内容主要是工程施工期间的水土保持质量控制、建设各方水土保持工作的组织和协调及有关水土保持的合同与信息管理。根据隐蔽 工程建设的实标情况和水土保持监理的特点,其工作程序如图所示。 2.水土保持监理工作内容 2.1施工准备监理
2.1.1组织水土保持监理交底会,向施工单位提出应特别注意的水土保持敏感因子和有关水土保持要求及监理的工作程序。
龙源期刊网 http://www.qikan.com.cn
2.1.2在单位工程开工前,对施工单位报送的单位工程施工组织设计中有关水土保持的内容进行审核,从水土保持的角度提出优化施工方案与方法的建议并答署意见,作为监理单位对施工组织审核意见的一部分。
2.1.3检查施工单位水土保持准备工作落实的情况。 2.2施工过程监理
2.2.1检查施工单位水土保持管理机构的运行情况,要求承包人在施工过程中按已经批准的施工组织设计中的水土保持措施和有关的审核意见进行文明施工,加强水土保持管理,做好施工中有关水土保持的原始资料收集、记录、整理和总结工作。
2.2.2检查施工过程中施工单位对承包合同中水土保持条款执行与措施落实等情况。 2.2.3现场水土保持监理主要采取巡视检查方式,并辅之一定的检测手段,对施工单位的水土保持工作进行跟踪检查和控制,作出定性和定量的评价。
2.2.4主持召开工程区域范围内与殊途保持有关的会议,对水土保持方面的意见进行汇总,审核施工单位提出的处理措施。